Culpable delay in construction contracts
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT). The contractor may (but is not necessarily) also be entitled to claim for loss and expense associated with the delay.
Culpable delay (sometimes referred to as 'contractor delay') on the other hand is a delay that is entirely the fault of the contractor. Where the contractor is culpable for a delay, they have no entitlement to an extension of time or loss and expense.
Where there is a culpable delay, the period of time after the contractual date for completion has passed is referred to as the period of contractor culpable delay, and during this period, the contractor will be liable to pay liquidated and ascertained damages (LAD's) to the client.
Concurrent delay refers to the complex situation where more than one event occurs at the same time, but where not all of those events enable the contractor to claim an extension of time. For more information, see Concurrent delay.
In Carillion Construction Ltd. v Woods Bagot Europe Ltd. and others [2016], the Technology and Construction Court (TCC) held that a subcontractor who had caused a delay, was also entitled to an extension of time and that this should run contiguously from the contractual completion date. This meant that the subcontractor’s period of culpable delay was extinguished, and they were no longer liable for their own delay.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
What it is and how to use it.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.