Culpable delay in construction contracts
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT). The contractor may (but is not necessarily) also be entitled to claim for loss and expense associated with the delay.
Culpable delay (sometimes referred to as 'contractor delay') on the other hand is a delay that is entirely the fault of the contractor. Where the contractor is culpable for a delay, they have no entitlement to an extension of time or loss and expense.
Where there is a culpable delay, the period of time after the contractual date for completion has passed is referred to as the period of contractor culpable delay, and during this period, the contractor will be liable to pay liquidated and ascertained damages (LAD's) to the client.
Concurrent delay refers to the complex situation where more than one event occurs at the same time, but where not all of those events enable the contractor to claim an extension of time. For more information, see Concurrent delay.
In Carillion Construction Ltd. v Woods Bagot Europe Ltd. and others [2016], the Technology and Construction Court (TCC) held that a subcontractor who had caused a delay, was also entitled to an extension of time and that this should run contiguously from the contractual completion date. This meant that the subcontractor’s period of culpable delay was extinguished, and they were no longer liable for their own delay.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.